WP8 – Dissemination, exploitation and communication

Lead Beneficiary Start month End month
CSIC 1 48

Objectives

The overall objective is to ensure proactive and efficient dissemination, exploitation and communication of the project results. Led by CSIC, this work package aims at maximising the project’s impact by optimising dissemination, exploitation and communication of results to the targeted audiences.

Tasks

Task# Task name Task leader Participants
8.1 Communication and dissemination plan, visual identity (M1-M48) CSIC All
8.2 Scientific dissemination activities (M3-M48) UCAM All
8.3 Outreach activities to engage stakeholders (M6-M48) HE All
8.4 Technical-Economic Assessment (M42 M48) SuperGrid Institute All

Deliverables

Deliverable# Deliverable name Lead beneficiary Type Due date (in months)
D8.1 Webpage and visual identity CSIC Websites, patent filings, videos, etc 3
D8.2 Communication and dissemination plan CSIC Document, report 4
D8.3 Exploitation plan SuperGrid Institute Document, report 24
D8.4 Stakeholders’ outreach activities HE Websites, patent filings, videos, etc 46
D8.5 Final dissemination and exploitation report CSIC Document, report 48
D8.6 Technical-Economic Assessment report SuperGrid Institute Document, report 48