Work packages

For2ensics is structured in 8 separate Work Packages (WPs). The work structure and key WP contacts are listed below:

Work Package No Work Package name Lead Beneficiary Effort (Person-Months) Start Month End Month Deliverable No(s)
WP1 Use cases and requirement definition SuperGrid Institute 37.00 1 12 D1.2, D1.1
WP2 SiC semiconductor material and devices HE 157.00 1 40 D2.2, D2.1, D2.4, D2.3
WP3 High Voltage Packaging DeepC 94.00 3 42 D3.1, D3.3, D3.2
WP4 Validation tests and reliability UBREMEN 154.00 1 48 D4.3, D4.2, D4.6, D4.5, D4.4, D4.1
WP5 Converter Components EPFL 74.00 6 45 D5.4, D5.5, D5.3, D5.2, D5.1
WP6 DC/DC Converter Demonstrator SuperGrid Institute 107.00 12 48 D6.3, D6.5, D6.4, D6.2, D6.1
WP7 Project management and Coordiantion CSIC 40.00 1 48 D7.3, D7.2, D7.1
WP8 Dissemination, exploitation and communication CSIC 44.00 1 48 D8.4, D8.1, D8.3, D8.2, D8.5, D8.6