WP7 – Project management and Coordiantion

Lead Beneficiary Start month End month
CSIC 1 48

Objectives

  • Coordinate the consortium with respect to project deadlines, costs and objectives, including deliverable and milestone monitoring;
  • Promptly manage scientific and technical risks;
  • Manage project meetings and the working platform and knowledge repository;
  • Manage and plan open science issues; 5) Deliver reports to the EC on schedule.

Tasks

Task# Task name Task leader Participants
7.1 Administrative coordination (M1-M48) CSIC All
7.2 Internal communication and meetings (M1-M48) CSIC All
7.3 Scientific coordination (M1-M48) SuperGrid Institute All
7.4 Open science management (M1-M48) CSIC All
7.5 Project risk management and innovation management (M1-M48) SuperGrid Institute All
7.6 Clustering activities with other EU funded initiatives (M1-M48) CSIC All

Deliverables

Deliverable# Deliverable name Lead beneficiary Type Due date (in months)
D7.1 Data management plan (DMP) CSIC Data Management Plan 6
D7.2 Risk management&innovation management plan (RM&IMP) CSIC Document, report 3
D7.3 Annual Project Reports CSIC Document, report 12